Removal of Tiles from a Traffigard deck, then preperation and installation of DecKing PVC Deck membrane                 
 hover your mouse curser over the photo for the text


original deck with Tiles over Traffigard the deck is leaking into the room below about dead centre of this picture
there is some minor ponding in the corner against the fence removal of the tiles is slow and labourious, here using a small electric hammer chisel
this area in the centre of the deck the plywood was wet underneath the Traffigard total destruction of the tiles
after a cleanup and a quick sanding the cause of the leak was found, a split in the Traffigard, along a plywood joint the Traffigard is scraped off and then the residual sanded off down to the plywood
some of the dents caused by the removal of the tiles are filled another view of the deck with filler and also a buildup at the upper edge with Covercol AB Rapid compound, to take out the ponding here
another view of the deck where the filler has been applied once dry the deck is sanded again and the Dec-King PVC membrane is installed
completed DecKing membrane looking towards the outlet completed DecKing membrane
 completed DecKing membrane looking at the internal corner and the finish under the door sill another view of the internal corner
a pvc coated metal drip edge was installed to the outside perimeter behind the fence palings, then the DecKing membrane welded to it done